The planned improvements to the junction of Hollymeok and Portnalls have been completed as planned and should assist in making these crossroads safer than has been the case.


As written in the previous newsletter the planned improvements to junction 8 of the M25 will take place throughout 2020, intending to ease congestion

This will involve;

Upgrading the traffic signal installation throughout the junction

Widening into the existing verge and extending the anti -clockwise exit slip road

Adding an extra lane on the north circulatory section of the roundabout

Widening lanes on the east and west bridge section of the roundabout

Improving road signs and markings

Widening and realignment on the A217 southbound to two lanes that merge prior to Wray lane.